E
Ehsan Khan
Hello again...
I tried to create a project for testing reasons.. Following are the steps
that I followed....
1) created a task assigned a resource to that
2) Made the duration of task to 3 days
3) Updated the progress on the task to 30% work complete
4) Then I edited the Units of the resource to 50%
Now wht happens is that:
1) The duration of this changed to 5.4 days??? why??? I changed the units
to 50% shouldn't the duration change to 6 days?? does the calculation take
into account the % work complete???
2) Also The % complete changed to 11% whereas % work complete changed to
20%?? why ??? I can't figure this out....
Now if in case I make the units to 100% again and try to update the % work
complete field ... the difference in % work complete and % complete stays in
place...... Please help me out....... its over my head..... how are these
field attached to each other?????????
Thanks..........................
I tried to create a project for testing reasons.. Following are the steps
that I followed....
1) created a task assigned a resource to that
2) Made the duration of task to 3 days
3) Updated the progress on the task to 30% work complete
4) Then I edited the Units of the resource to 50%
Now wht happens is that:
1) The duration of this changed to 5.4 days??? why??? I changed the units
to 50% shouldn't the duration change to 6 days?? does the calculation take
into account the % work complete???
2) Also The % complete changed to 11% whereas % work complete changed to
20%?? why ??? I can't figure this out....
Now if in case I make the units to 100% again and try to update the % work
complete field ... the difference in % work complete and % complete stays in
place...... Please help me out....... its over my head..... how are these
field attached to each other?????????
Thanks..........................