S
Shahriar Nour Khondokar
During the tracking phase of a project, if I am tracking by 'Work', if i
insert/update the value for '% Work complete', the value for 'Work remaining'
changes as expected. But the duration value is not changing at all.
Is it possible to make the 'duration' value to change along with change in
'% Work complete' value?
Is there any way to account for cases where the actual 'Work' value exceeds
the estimated 'Work' value; i.e. '% Work complete value' greater than 100%?
insert/update the value for '% Work complete', the value for 'Work remaining'
changes as expected. But the duration value is not changing at all.
Is it possible to make the 'duration' value to change along with change in
'% Work complete' value?
Is there any way to account for cases where the actual 'Work' value exceeds
the estimated 'Work' value; i.e. '% Work complete value' greater than 100%?