Hi,
i am searching for a solution that a milestones starts with the firs
starting date out of several defined processes.
example:
milestone:
- start of picking season
process:
- banana picking date: 25.03.2010
- apple picking date: 22.03.2010
- picking party date: 20.03.2010
==> the milestone shall get the date of the 20.03. However, if one o
the other processes would be moved to an earlyer date, this date shoul
be taken.
How do i have to set the relationships in MSP to achieve this? + whic
other adjustments to i have to take?
thx a lot, rgds ökne
i am searching for a solution that a milestones starts with the firs
starting date out of several defined processes.
example:
milestone:
- start of picking season
process:
- banana picking date: 25.03.2010
- apple picking date: 22.03.2010
- picking party date: 20.03.2010
==> the milestone shall get the date of the 20.03. However, if one o
the other processes would be moved to an earlyer date, this date shoul
be taken.
How do i have to set the relationships in MSP to achieve this? + whic
other adjustments to i have to take?
thx a lot, rgds ökne