H
Heitmann
I have a problem with MS project 2003 professional, which sometimes
stores
links to subprojects as absolute paths. I want relative path references
for
subprojects, so that they are included from the same folder where the
main
project is. How can I impose this? Details follow:
I have a master project, including subprojects, some of which are
linked
between each other by task dependencies. I got the whole set of files
as a zip
file. I unzipped them to a directory on a shared folder of a MS windows
server
2003 computer. Then I started making modifications to individual files;
before
each major modification, I copied the whole folder to a new one (v1.5
-> v1.6...),
in order to have complete snapshots of the project evolution at
previous times.
At a certain point, MS project started to link the subprojects using
absolute
paths: The master project in the v1.6 folder thus referred to
subprojects e.g.
in the v1.5 folder. The only way to circumvent this was to reassign
manually
each subproject to the new folder. I cannot do this procedure at each
update
of the project.
I tried to go back to the zipped folder, and created test versions,
which
however had all relative paths, which is what I wanted. The whole thing
looks
like a bug to me (unpredictable behaviour). I tried also to save the
folder
to the local disk of my computer; it maintains the path reference to
the
shared folder even if the network is not connected (then it says it
doesn't
find the files).
So my question is: how/where can I ask that subproject tasks are
looked up
in paths relative from the main project? E.g. "SubProj1.mpp" instead
of
C:\projects\v1.5\SubProj1.mpp"?
stores
links to subprojects as absolute paths. I want relative path references
for
subprojects, so that they are included from the same folder where the
main
project is. How can I impose this? Details follow:
I have a master project, including subprojects, some of which are
linked
between each other by task dependencies. I got the whole set of files
as a zip
file. I unzipped them to a directory on a shared folder of a MS windows
server
2003 computer. Then I started making modifications to individual files;
before
each major modification, I copied the whole folder to a new one (v1.5
-> v1.6...),
in order to have complete snapshots of the project evolution at
previous times.
At a certain point, MS project started to link the subprojects using
absolute
paths: The master project in the v1.6 folder thus referred to
subprojects e.g.
in the v1.5 folder. The only way to circumvent this was to reassign
manually
each subproject to the new folder. I cannot do this procedure at each
update
of the project.
I tried to go back to the zipped folder, and created test versions,
which
however had all relative paths, which is what I wanted. The whole thing
looks
like a bug to me (unpredictable behaviour). I tried also to save the
folder
to the local disk of my computer; it maintains the path reference to
the
shared folder even if the network is not connected (then it says it
doesn't
find the files).
So my question is: how/where can I ask that subproject tasks are
looked up
in paths relative from the main project? E.g. "SubProj1.mpp" instead
of
C:\projects\v1.5\SubProj1.mpp"?