Hi,
1. Is ther any automatic option to set the % coplete that will be
relative to the start and finish date? (i.e. if the task duration is
10 days and they finished 5 days of work I would like to write 50%)
2. What is the meaning of "late" in the "status" (or status indicator)
culomn?
i.e. I see Late on a task that steal have time to finish (finish date
is on august. here is the task copy:
Task name duration
status start date finish date
Writing Technical Spec. Approval (TSA) 55 days Late Thu 17/05/07
Sun 05/08/07
I put 85% that completed
1. Is ther any automatic option to set the % coplete that will be
relative to the start and finish date? (i.e. if the task duration is
10 days and they finished 5 days of work I would like to write 50%)
2. What is the meaning of "late" in the "status" (or status indicator)
culomn?
i.e. I see Late on a task that steal have time to finish (finish date
is on august. here is the task copy:
Task name duration
status start date finish date
Writing Technical Spec. Approval (TSA) 55 days Late Thu 17/05/07
Sun 05/08/07
I put 85% that completed