L
Leslie Isaacs
Hello All
I have a very complex, A2K frontend/backend split mdb, which is often now
used by 7 users at the same time. The backend sits on a server machine
running Windows2K Server, and is approaching 1Gb. I know that sooner or
later I should move to SQLserver, but do not have the expertise to do this
myself and cannot afford to buy it in yet (hopefully in a year or so!).
Until I can move to SQLServer, I was wondering whether a solution might be
to split the backend in half (or even into thirds), and get the users then
to relink the tables of their frontend to whichever backend they need (from
the actual usage point of view of the users this would be perfectly
feasible, and would probably only need to be done once - at the start of
each day). That way the 7 users would be very unlikely all to be using the
same backend at the same time, and each backend would obviously be half (or
third) of the size of the original backend.
Is there any reason why this idea would not be a good one? Obviously another
idea would be simply to have 2 (or 3) separate frontends which link to the 2
(or 3) cutdown backends, but that way I would have to maintain 2 (or 3)
frontends and as I am regularly required to make amendments to the frontend
this would be tedious and carry the risk of the frontends becoming
inconsistent with each other.
Hope someone can help.
Many thanks
Leslie Isaacs
I have a very complex, A2K frontend/backend split mdb, which is often now
used by 7 users at the same time. The backend sits on a server machine
running Windows2K Server, and is approaching 1Gb. I know that sooner or
later I should move to SQLserver, but do not have the expertise to do this
myself and cannot afford to buy it in yet (hopefully in a year or so!).
Until I can move to SQLServer, I was wondering whether a solution might be
to split the backend in half (or even into thirds), and get the users then
to relink the tables of their frontend to whichever backend they need (from
the actual usage point of view of the users this would be perfectly
feasible, and would probably only need to be done once - at the start of
each day). That way the 7 users would be very unlikely all to be using the
same backend at the same time, and each backend would obviously be half (or
third) of the size of the original backend.
Is there any reason why this idea would not be a good one? Obviously another
idea would be simply to have 2 (or 3) separate frontends which link to the 2
(or 3) cutdown backends, but that way I would have to maintain 2 (or 3)
frontends and as I am regularly required to make amendments to the frontend
this would be tedious and carry the risk of the frontends becoming
inconsistent with each other.
Hope someone can help.
Many thanks
Leslie Isaacs