S
Stephan Steiner
Hi
Today we discovered that the project we're using to report
unproductive hours (Holidays, Compensation, unpaid holidays, etc.)
exhibits some peculiarities:
In each employee's timesheet (PWA), all those unproductive tasks have
the remaining work value set to 0, the actual work set to the number
of hours previously reported, and the work set to the same value.
If the project is opened in the project client, the work corresponds
to the value in the PWA - however, the remaining work now corresponds
to work, whereas actual work is 0.
All this is for tasks that do not have the update flag set (so the
employee has reported the hours back to the project manager, which
approved the hours).
Does anybody have an idea how this discrepancy could have happened and
how to resolve it?
Regards
Stephan
Today we discovered that the project we're using to report
unproductive hours (Holidays, Compensation, unpaid holidays, etc.)
exhibits some peculiarities:
In each employee's timesheet (PWA), all those unproductive tasks have
the remaining work value set to 0, the actual work set to the number
of hours previously reported, and the work set to the same value.
If the project is opened in the project client, the work corresponds
to the value in the PWA - however, the remaining work now corresponds
to work, whereas actual work is 0.
All this is for tasks that do not have the update flag set (so the
employee has reported the hours back to the project manager, which
approved the hours).
Does anybody have an idea how this discrepancy could have happened and
how to resolve it?
Regards
Stephan