Remaining Availability

  • Thread starter J Burford Fields
  • Start date
J

J Burford Fields

After making sure all the names were identical, I copied tasks into a
combined project file. Next I took a look at the Resource Usage
screen, right clicked in the numbers area and set it to show "remaining
availability."

It's impressive until someone noticed that resources had 160 hours of
remaining availability in a single week. Woops!

I take it that this fields is adding up the available time from each
project copied into the master project?

J
 