C
Casey
I have a project that where we received a short additional task order last
month. A separate file was developed with the WBS for the new work. When I
copy the tasks and paste them into my original plan, then rebaseline the NEW
tasks only, update the status date, set the % complete to 100% (the new work
actually completed on 3/30), this is what happens: most fields calculate
properly (BCWS, BCWP, ACWP, and EAC); however the “Remaining Cost†for almost
all tasks is equal to the BCWS/BCWP/ACWP (remember all work is completed).
For a few tasks, remaining costs are $0. Any ideas? I have tried a million
different combinations of steps. Using MS Project 2003 with SP1.
month. A separate file was developed with the WBS for the new work. When I
copy the tasks and paste them into my original plan, then rebaseline the NEW
tasks only, update the status date, set the % complete to 100% (the new work
actually completed on 3/30), this is what happens: most fields calculate
properly (BCWS, BCWP, ACWP, and EAC); however the “Remaining Cost†for almost
all tasks is equal to the BCWS/BCWP/ACWP (remember all work is completed).
For a few tasks, remaining costs are $0. Any ideas? I have tried a million
different combinations of steps. Using MS Project 2003 with SP1.