Laura
Thanks in advance for any help in this frustrating scenario... I have an RDU
of 11 days and have asked for the project to reschedule remaining work as of
12/26/04. The calendar of the project is an 8hr day, weekends worked. There
are no resources on the task. The finish date as calculated is 12/30/04.
Based upon the calendar, it seems that it should finish after the 1st of the
year. I have even removed all predecessors. Constraint Type is ASAP. There
is an actual start date on the task and a percent complete.
Any ideas??? Thanks...