J
JJ
I want to include % Complete and Remaining Duration when request a
status update from people responsible for tasks on a schedule. Since
each one affects the other, how do I implement the status I receive
such that I fulfill both requirements.
For example:
Task A Duration: 20-day task
Task Status after Week 1:
Task A % Complete = 25%
Task A Remaining Duration = 25 days
How should this be implemented in Project?
status update from people responsible for tasks on a schedule. Since
each one affects the other, how do I implement the status I receive
such that I fulfill both requirements.
For example:
Task A Duration: 20-day task
Task Status after Week 1:
Task A % Complete = 25%
Task A Remaining Duration = 25 days
How should this be implemented in Project?