I am able to create an s curve with BCWS and BCWP and convert it to a planned
vs. actual percentage curve using BAC. What I need to do is also forecast
remaining BCWP/ACWP to end of project on the same curve to show how project
is tracking until 100% complete. How do I do this, exactly!