Hello!
We update the projects by entering a number of actual hours and the
resources also have an option of adjusting remaining hours if there are any
changes. I am having a problem when resources try to change the remaining
hours. For example, I have a duration set for 3 days (24 hours), my resource
puts in 8 hours for the task and changes the remainder to 5 hours instead of
16. After this update published to the project, my project plan shows
correctly 5 hours remaining and 62% complete, meanwhile the resource's task
menu shows that he only has 1 hour remaining and 92% complete. What could be
causing this? It's the only resource on this task and on the tasks with
remaining work staying the same we didn't have any issues - the remaining
hours and % complete in the project plan matched what the resource has in its
task view.
Any help is really appreciated. Thanks a lot!
Elvira LeNoir
We update the projects by entering a number of actual hours and the
resources also have an option of adjusting remaining hours if there are any
changes. I am having a problem when resources try to change the remaining
hours. For example, I have a duration set for 3 days (24 hours), my resource
puts in 8 hours for the task and changes the remainder to 5 hours instead of
16. After this update published to the project, my project plan shows
correctly 5 hours remaining and 62% complete, meanwhile the resource's task
menu shows that he only has 1 hour remaining and 92% complete. What could be
causing this? It's the only resource on this task and on the tasks with
remaining work staying the same we didn't have any issues - the remaining
hours and % complete in the project plan matched what the resource has in its
task view.
Any help is really appreciated. Thanks a lot!
Elvira LeNoir