Remaining resource availability assignement

  • Thread starter Sebastián Streiger
  • Start date
S

Sebastián Streiger

Hi fellows:
I have a resource that is assigned 50% on a task that starts 01/01/2005.
That task finishes on 01/03/2005.
I have other task that starts on 01/02/2005. I would like to assign to this tast the maximum available each day.
I mean I want it to have assigned 50% of the resource for days 01/02/2005 and 01/03/2005. Then on the task should be assigned the 100% of the resource.
I would like it automátically, so any reschedulling or modifications reasigns the remaining availability to taht task.

Is there a way to do this?

Best regards
 
D

Dale Howard [MVP]

Sebastian --

There is no automatic way to do this. You can manually perform this operation, however, by assigning the resource to the second task at 50% units, applying the Task Usage view, and then editing the Work in the timephased grid to show 8 hours per day on the last part of the task. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Hi fellows:
I have a resource that is assigned 50% on a task that starts 01/01/2005.
That task finishes on 01/03/2005.
I have other task that starts on 01/02/2005. I would like to assign to this tast the maximum available each day.
I mean I want it to have assigned 50% of the resource for days 01/02/2005 and 01/03/2005. Then on the task should be assigned the 100% of the resource.
I would like it automátically, so any reschedulling or modifications reasigns the remaining availability to taht task.

Is there a way to do this?

Best regards
 
S

Sebastián Streiger

Dale:
I found a way similar to the one you described using the "Resource usage view".
Both view look very similar. As far as I can see the only difference is the grouping.

Thanks for your help.

Best regards


--
Sebastián Streiger

"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> escribió en el mensaje Sebastian --

There is no automatic way to do this. You can manually perform this operation, however, by assigning the resource to the second task at 50% units, applying the Task Usage view, and then editing the Work in the timephased grid to show 8 hours per day on the last part of the task. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Hi fellows:
I have a resource that is assigned 50% on a task that starts 01/01/2005.
That task finishes on 01/03/2005.
I have other task that starts on 01/02/2005. I would like to assign to this tast the maximum available each day.
I mean I want it to have assigned 50% of the resource for days 01/02/2005 and 01/03/2005. Then on the task should be assigned the 100% of the resource.
I would like it automátically, so any reschedulling or modifications reasigns the remaining availability to taht task.

Is there a way to do this?

Best regards
 
D

Dale Howard [MVP]

Sebastian --

The Task Usage and Resource Usage views are both assignment views, and therefore, you can perform the steps in either view. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Dale:
I found a way similar to the one you described using the "Resource usage view".
Both view look very similar. As far as I can see the only difference is the grouping.

Thanks for your help.

Best regards


--
Sebastián Streiger

"Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com> escribió en el mensaje Sebastian --

There is no automatic way to do this. You can manually perform this operation, however, by assigning the resource to the second task at 50% units, applying the Task Usage view, and then editing the Work in the timephased grid to show 8 hours per day on the last part of the task. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Hi fellows:
I have a resource that is assigned 50% on a task that starts 01/01/2005.
That task finishes on 01/03/2005.
I have other task that starts on 01/02/2005. I would like to assign to this tast the maximum available each day.
I mean I want it to have assigned 50% of the resource for days 01/02/2005 and 01/03/2005. Then on the task should be assigned the 100% of the resource.
I would like it automátically, so any reschedulling or modifications reasigns the remaining availability to taht task.

Is there a way to do this?

Best regards
 