Hi fellows:
I have a resource that is assigned 50% on a task that starts 01/01/2005.
That task finishes on 01/03/2005.
I have other task that starts on 01/02/2005. I would like to assign to this tast the maximum available each day.
I mean I want it to have assigned 50% of the resource for days 01/02/2005 and 01/03/2005. Then on the task should be assigned the 100% of the resource.
I would like it automátically, so any reschedulling or modifications reasigns the remaining availability to taht task.
Is there a way to do this?
Best regards
I have a resource that is assigned 50% on a task that starts 01/01/2005.
That task finishes on 01/03/2005.
I have other task that starts on 01/02/2005. I would like to assign to this tast the maximum available each day.
I mean I want it to have assigned 50% of the resource for days 01/02/2005 and 01/03/2005. Then on the task should be assigned the 100% of the resource.
I would like it automátically, so any reschedulling or modifications reasigns the remaining availability to taht task.
Is there a way to do this?
Best regards