C
confused
there is a task that has several resources assigned to it. The task still
has remaining work, but the resource has completed his work, actual start /
finish dates have been filled in. In hindsite, the resource really didn't
finish the task and so in the resource usage view 40h of remaining work was
added. MSP did add 40 h but in increments of .08h per day which extended the
end date of the task by several months. Why didn't it add 8h per day which
is the resources available time?
has remaining work, but the resource has completed his work, actual start /
finish dates have been filled in. In hindsite, the resource really didn't
finish the task and so in the resource usage view 40h of remaining work was
added. MSP did add 40 h but in increments of .08h per day which extended the
end date of the task by several months. Why didn't it add 8h per day which
is the resources available time?