Remaining Work and % complete

V

Vit

Hi all,

I'm trying to understand how it works....

if I insert remaining work 0, the % complete doesn't change.... it
should be 100%... or not???

what I'm doing wrong???

thank you so much...

cheers

Vit
 
J

JulieS

Hello Vit,

If you have disabled the option "Updating task status updates resource
status" you will need to manually change % complete, although % Work
Complete should be correct. Check your setting in Tools > Options,
Calculation tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


in message
news:a8c1bf92-d0f5-4b83-a985-987f0d51be2f@n33g2000pri.googlegroups.com...
 