Remaining work and Timesheets PS2007

B

boggyboy

after installing the July Infrastructure update, i found a number of issues
with the new ability to enter remaining work on Timesheets. are others using
it now? is it working out?
 
D

Dale Howard [MVP]

boggyboy --

What issues are you finding? Please be specific, as that would help all of
us. Regarding using the Remaining Work column in the My Timesheet page, the
field is locked unless your Project Server administrator selects the "Time
entry by Timesheet only" option on the Task Settings and Display page. Hope
this helps.
 