Remaining work and % work complete

P

Perl

Hello,

One of my resources update actual work from PWA. and change remaining work
to 0 hours.
At % work complete column he gets 96%. why not 100% ?

BTW, I accept his update. At MSP I see that task is complete.

Any Idea ?

Perl
 
M

Mvisscher

In 2007 the user has to click the Recalculate button at the bottom of the
screen in PWA to update the % complete and other fields.

Marcel Visscher
 
P

Perl

We have 2003 version.


Mvisscher said:
In 2007 the user has to click the Recalculate button at the bottom of the
screen in PWA to update the % complete and other fields.

Marcel Visscher
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top