P
Perl
Hello,
We have Project Server 2003.
One of my resources update actual work from PWA. and change remaining work
to 0 hours.
At % work complete column he gets 96%. why not 100% ?
BTW, I accept his update. At MSP I see that task is complete.
Any Idea ?
Perl
We have Project Server 2003.
One of my resources update actual work from PWA. and change remaining work
to 0 hours.
At % work complete column he gets 96%. why not 100% ?
BTW, I accept his update. At MSP I see that task is complete.
Any Idea ?
Perl