Remaining work for resources

S

Scott A

Is there a way to get a view like Resource Usage to show the Remaining work
for tasks in the time portion of the view - not the total amount of work?

An example is that I have a task that has 12 days of work and 9 have been
completed. In the time portion of the view it shows 12 days in the time
period of the task. I would like it to show 3 days - the remaining work.
 
J

Jan De Messemaeker

Hi Scott,

You can show both Work and Actal Work (Remaining being the difference) but
not Remaining Work as such.
HTH
 
J

JulieD

Hi Scott

in Resource Usage you can get actual work to be displayed .. right mouse
click just under Details on the RHS and choose Actual Work.

On the LHS you can insert the Remaining Work column.

Cheers
JulieD
 
G

Gérard Ducouret

Hello scott,
In the Resource Usage view, display the Actual Work field besides the
(Scheduled) Work
If a cell of Work as not any value in the Actual Work cell in front of it,
that means it's Remaining work...
Hope this helps,

Gérard Ducouret
 