S
Scott A
Is there a way to get a view like Resource Usage to show the Remaining work
for tasks in the time portion of the view - not the total amount of work?
An example is that I have a task that has 12 days of work and 9 have been
completed. In the time portion of the view it shows 12 days in the time
period of the task. I would like it to show 3 days - the remaining work.
for tasks in the time portion of the view - not the total amount of work?
An example is that I have a task that has 12 days of work and 9 have been
completed. In the time portion of the view it shows 12 days in the time
period of the task. I would like it to show 3 days - the remaining work.