M
Mike
I have an issue with MSP 2k3 SP2 (Enterprise) and I'm not quite sure
if it's actually a technical bug or just something I'm doing wrong.
I am the administrator for a large corporation. I have many cases
where people will leave the company and the project plan owner will
leave remaining work hours for a resource I deactivated, causing a
typical spooler error, etc. This situation happens frequently and is
obviously easily resolved by removing the remaining hours and setting
the resource to proposed.
However, this particular plan, something odd is going on. I have a
resource that is inactive that has 1 remaining hour on a single task
on one plan. The plan owner said he was getting a spooler error. I
walked to his desk and started to coach him on how to remove the time,
etc. I had him save the plan after the time was removed and exit.
The next time he opened the plan, MSP said "Your actuals may be out of
synch with the server's, do you wish to synch?" After he
synchronized, the *remaining* hour returned to that resource.
I have tried everything I can think of to remove this hour. I
reactivated the resource, opened their timesheet and checked for any
oddities or time that may have been stuck out in limbo. I had the
owner accept all time and fully update the plan. etc, etc.
Each and every time I remove this remaining hour, it somehow ends up
back in the plan when you synchronize actuals from the server, ergo
the spooler error returns.
Has anyone seen this? Let me know if you need more data.
Kind regards,
Mike H,
if it's actually a technical bug or just something I'm doing wrong.
I am the administrator for a large corporation. I have many cases
where people will leave the company and the project plan owner will
leave remaining work hours for a resource I deactivated, causing a
typical spooler error, etc. This situation happens frequently and is
obviously easily resolved by removing the remaining hours and setting
the resource to proposed.
However, this particular plan, something odd is going on. I have a
resource that is inactive that has 1 remaining hour on a single task
on one plan. The plan owner said he was getting a spooler error. I
walked to his desk and started to coach him on how to remove the time,
etc. I had him save the plan after the time was removed and exit.
The next time he opened the plan, MSP said "Your actuals may be out of
synch with the server's, do you wish to synch?" After he
synchronized, the *remaining* hour returned to that resource.
I have tried everything I can think of to remove this hour. I
reactivated the resource, opened their timesheet and checked for any
oddities or time that may have been stuck out in limbo. I had the
owner accept all time and fully update the plan. etc, etc.
Each and every time I remove this remaining hour, it somehow ends up
back in the plan when you synchronize actuals from the server, ergo
the spooler error returns.
Has anyone seen this? Let me know if you need more data.
Kind regards,
Mike H,