Remaining Work in My Tasks formated in hours (2007)

S

ST

In PWA 2007, is it possible to have Remaining Work within My Tasks formated
in hours instead of the default of days?

/Spiro Theopoulos
 
D

Dale Howard [MVP]

ST --

Yes. First of all, you need to make sure you have SP1 applied to Project
Server 2007. You can then edit the My Tasks web part and specify that Work
is displayed in Hours rather than days. Refer to my response to your
previous question about setting up Managed Time Periods and you will find
the steps listed for edting the My Tasks web part.

Since it appears you are pretty new to Project Server 2007, you might want
to consider purchasing our books on the tool at:

http://www.projectserverbooks.com

Hope this helps.
 
D

Darrell

Yes,

On the My Tasks page open the properties of the web part from the "Site
Actions" button (top right of page), edit, modify shared web part

In the Project Web Access section you can set the options for the duration
and work formats.

Darrell
 