Remaining work in Timehseet view

S

shima

Hi,
i am administrator of pwa 2007.How do I get remaining work to appear in the
timesheet in the task view in
PWA. My default method of tracking is set to: Actual work done Resources
report the actual work done. i wanna my resources can report remainig time of
work in their timesheet.

HELP and thanks in advance
 
D

Dale Howard [MVP]

shima --

You cannot add the Remaining Work column to the My Timesheet page. This
means that team members need to adjust Remaining Work on the My Tasks page.
Hope this helps.
 