Hello everyone.
Just installed infrastructure update and added remaining work to the
timesheet view .
2 issues:
1-It is in days and the rest of the info is in hours in the timesheet.
Anybody knows how to change remaining work in hours in the timesheet ?
2-If it is displayed in days, the value displayed is not the same as in My
Tasks or in the project plan. Project starts with the remaining work in
hours from the plan (assignement) and converts it based on an 8hour/day
calendar (which is not our case...). So 7h or work remaining becomes .875d in
My timesheet. Anybody else noticed this ?
Suggestions welcome...
Tx in advance
Chris
Just installed infrastructure update and added remaining work to the
timesheet view .
2 issues:
1-It is in days and the rest of the info is in hours in the timesheet.
Anybody knows how to change remaining work in hours in the timesheet ?
2-If it is displayed in days, the value displayed is not the same as in My
Tasks or in the project plan. Project starts with the remaining work in
hours from the plan (assignement) and converts it based on an 8hour/day
calendar (which is not our case...). So 7h or work remaining becomes .875d in
My timesheet. Anybody else noticed this ?
Suggestions welcome...
Tx in advance
Chris