G
GSW407
We are finding that the remaining work and actual work between the task
level and the resources level is out-of-sync.
We imported a project plan from MS Project to Project Server. We have
been live for three weeks. Resources are entering their time through
PWA and time is being accepted daily by the project manager.
We are finding that the Remaining Work hours and Actual Work hours are
not changing at the task level. When we view the resources, we can see
that actual work has been updated and that remaining work has been
reduced in hours.
One interesting note: For tasks that we entered later that were entered
directly into Project Server, the task level remaining work and actual
work IS in sync with the resource level.
Any thoughts on how we can resync our remaining work and actual work
and have it update as it should?
level and the resources level is out-of-sync.
We imported a project plan from MS Project to Project Server. We have
been live for three weeks. Resources are entering their time through
PWA and time is being accepted daily by the project manager.
We are finding that the Remaining Work hours and Actual Work hours are
not changing at the task level. When we view the resources, we can see
that actual work has been updated and that remaining work has been
reduced in hours.
One interesting note: For tasks that we entered later that were entered
directly into Project Server, the task level remaining work and actual
work IS in sync with the resource level.
Any thoughts on how we can resync our remaining work and actual work
and have it update as it should?