K
k2me
We are using Project Server 2003. When looking at the Resource Usage View in
Schedule A, I can insert columns to see the Remaining Work, Work, Actual
Work, etc. for the enterprise resources. This view shows information both for
the tasks on Schedule A and also the totals for other schedules. I have a
situation where a certain resource has zero hours remaining on Schedule B
(and verified by looking at Schedule B in MS Project Professional). However,
when I open Schedule A and look at the Resource Usage view, it says that the
resource has 1,072.5 hours in Remaining Work for Schedule B. Does anyone have
an explanation for why this is happening (and how to fix it)?
Thank you.
Schedule A, I can insert columns to see the Remaining Work, Work, Actual
Work, etc. for the enterprise resources. This view shows information both for
the tasks on Schedule A and also the totals for other schedules. I have a
situation where a certain resource has zero hours remaining on Schedule B
(and verified by looking at Schedule B in MS Project Professional). However,
when I open Schedule A and look at the Resource Usage view, it says that the
resource has 1,072.5 hours in Remaining Work for Schedule B. Does anyone have
an explanation for why this is happening (and how to fix it)?
Thank you.