Remaining Work Incorrect in Resource Usage View

K

k2me

We are using Project Server 2003. When looking at the Resource Usage View in
Schedule A, I can insert columns to see the Remaining Work, Work, Actual
Work, etc. for the enterprise resources. This view shows information both for
the tasks on Schedule A and also the totals for other schedules. I have a
situation where a certain resource has zero hours remaining on Schedule B
(and verified by looking at Schedule B in MS Project Professional). However,
when I open Schedule A and look at the Resource Usage view, it says that the
resource has 1,072.5 hours in Remaining Work for Schedule B. Does anyone have
an explanation for why this is happening (and how to fix it)?

Thank you.
 
K

k2me

Thanks for the quick response, Dale. Wow, that's a bummer. So the schedule
owner will have to open all the schedules their resources are on to see the
correct numbers? Are there any other views that might work better to see how
resources are allocated?
 
D

Dale Howard [MVP]

k2me --

I would recommend that you use the View Resource Assignments view in PWA or
the View Resource Availability feature from the Resource Center page in PWA.
Hope this helps.
 