A
Alain
I have project server 2007 with IU installed.
In My Timesheet, I have the column "Remaining work". I would like that the
resources only fill the timesheet and than import their timesheets in "My
Task". My problem is that the "Remaining work" column in My Timesheet is read
only ! So the resources must go to "My Task" to adjust the remaining work
(and I don't want to do this).
How can I make this "Remaining work" in My Timesheet Read/Write ?
Thanks.
In My Timesheet, I have the column "Remaining work". I would like that the
resources only fill the timesheet and than import their timesheets in "My
Task". My problem is that the "Remaining work" column in My Timesheet is read
only ! So the resources must go to "My Task" to adjust the remaining work
(and I don't want to do this).
How can I make this "Remaining work" in My Timesheet Read/Write ?