I'm running into a recuring issue in several of my projects.
On some tasks that have little to no remaining work left and that are often
not even published, I often notice after opening the project plan that there
is a large amount of remaining work left. This happens on random resources
and I sometime get a warning that opening the file will interupt the
syncrhonization.
I have MS Project 2007 sp2 and we run Project server 2007 sp1
On some tasks that have little to no remaining work left and that are often
not even published, I often notice after opening the project plan that there
is a large amount of remaining work left. This happens on random resources
and I sometime get a warning that opening the file will interupt the
syncrhonization.
I have MS Project 2007 sp2 and we run Project server 2007 sp1