Remaining Work not matching Work on Usage Task View

J

Jow

I have a plan that shows 22 hours of "Remaining Work" for
a task. But when I look at the Task Usage for the same
task, there is 44 hours of "work" scheduled. There is
only one resource assigned to this task. Why would this
happen?
 
G

Gérard Ducouret

Hello Jow,

May be the assigned resource has an Actual Work of 22 hours ?

Gérard Ducouret
 
G

Guest

I am not sure what happend, but I am using the Workgroup
feature, and after I updated the resources actual hours
automatically, everything appeared fine.

Thanks anyway.
 