Shane
Hi All,
We have a project who have an issue with the value of remaining work not
reflecting correctly after updates.
The Project uses MOPS 2003
They use the tracking setting "Hours of work done per day or per week" and
Managed Time Periods. Their PMs are also forced to use these tracking
settings.
Here is the scenario:
Team member submits hours for the week including any remaining work for the
task. The PM accepts the work but after the replication with the workplan,
the remaining work value reverts back to its value before the manual change.
I hope this makes sense
Really appreciate anyones input/advice.
Cheers
Shane
We have a project who have an issue with the value of remaining work not
reflecting correctly after updates.
The Project uses MOPS 2003
They use the tracking setting "Hours of work done per day or per week" and
Managed Time Periods. Their PMs are also forced to use these tracking
settings.
Here is the scenario:
Team member submits hours for the week including any remaining work for the
task. The PM accepts the work but after the replication with the workplan,
the remaining work value reverts back to its value before the manual change.
I hope this makes sense
Really appreciate anyones input/advice.
Cheers
Shane