A
ahmed
I am experienceing an issue with administrative projects that I have not seen
before. Users are entering their time in PWA for admin tasks and the
Remaining Work field adjusts to show the time they entered. Has anyone seen
this before? I have tried synching to acutals and republishing the tasks but
it still shows in PWA on the resource's timesheet. Oddly enougugh the
remaing work column in Project Pro shows 0 hours.
before. Users are entering their time in PWA for admin tasks and the
Remaining Work field adjusts to show the time they entered. Has anyone seen
this before? I have tried synching to acutals and republishing the tasks but
it still shows in PWA on the resource's timesheet. Oddly enougugh the
remaing work column in Project Pro shows 0 hours.