Hello (This is a second post, not sure if the first worked or not)

I need to export timescaled Remaining work to Excel. Reading the MSP
help on timescale method does not show Rem work. I know Rem Work =
Actual - Work - how can I get this in a timescaled fashion?

Thank you!

arectoo
 
J

John

RC said:
Hello (This is a second post, not sure if the first worked or not)

I need to export timescaled Remaining work to Excel. Reading the MSP
help on timescale method does not show Rem work. I know Rem Work =
Actual - Work - how can I get this in a timescaled fashion?

Thank you!

arectoo

erectoo,
Well it's pretty straightforward, just get the timescaled values for
actual and work and do the subtraction in your code.

John