P
Peter
In the PWA Timesheet one of my resources indicated that the remaining work on
a task was 0. When the 0 was entered, the % Work Complete changed to 100% in
the timesheet, which is what is supposed to happen. (There was only one
resource assigned to the task and the task was not a summary task). The task
was approved but when it was "Updated" and electronically incorporated into
Project Pro, the task did not show that it had been completed.
Any suggestions why a task has 0 remaining hours in the PWA timesheet but is
not shown as complete in Project Pro will be appreciated.
a task was 0. When the 0 was entered, the % Work Complete changed to 100% in
the timesheet, which is what is supposed to happen. (There was only one
resource assigned to the task and the task was not a summary task). The task
was approved but when it was "Updated" and electronically incorporated into
Project Pro, the task did not show that it had been completed.
Any suggestions why a task has 0 remaining hours in the PWA timesheet but is
not shown as complete in Project Pro will be appreciated.