Cindy:
If you're using Project Server 2003 and you integrate PWA
with Outlook, you can use Outlook to send reminders.
If you're using stand alone, try building a custom field
with a graphical indicator. These seem to get everyone's
attention. Or try something simple, like changing the
font color.
Hope this helps!
----------------------
Sean Pales
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com
-----Original Message-----
Is there a way to attach a reminder to a task without
setting a deadline or a contraint?