Remove "completed" task from PWA Task List

J

Joe

Is there an update query or SP I can run to remove specific completed tasks
from a resources timesheet without having to use the “Clean up Project Server
database†feature from the Admin screen. The reason I don’t want to use this
feature is because it removes all completed items across all projects on the
server, which I don’t want to do.

NOTE: I am not looking to removed "DELETED" task from PWA.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.