Hi,
I have one problem. I can't remove one ent.field from project pland. Field
duration1 (task). How I'm removing it:
1. Open ent. global
2. Open "cust. ent. fields" and find this duration1 in "task"
3. Return all to default (remove any formulas, indicators and other)
4. Remove this field from ent. in tools -> organizer
5. Save ent global
6. Start project pro and remove it from cached ent.global in organizer
And..
When I'm starting new project - there is no duration1 field.
But then I'm openning some of old project's - it's there.
How to remove it from all saved at server projects??
How to remove it from all computers (if problem in cached ent.global) in
organization?
Thank's!!
Alerxander Barvinsky
pm4pm.org
I have one problem. I can't remove one ent.field from project pland. Field
duration1 (task). How I'm removing it:
1. Open ent. global
2. Open "cust. ent. fields" and find this duration1 in "task"
3. Return all to default (remove any formulas, indicators and other)
4. Remove this field from ent. in tools -> organizer
5. Save ent global
6. Start project pro and remove it from cached ent.global in organizer
And..
When I'm starting new project - there is no duration1 field.
But then I'm openning some of old project's - it's there.
How to remove it from all saved at server projects??
How to remove it from all computers (if problem in cached ent.global) in
organization?
Thank's!!
Alerxander Barvinsky
pm4pm.org