L
lhankg
I am running a very large constrction project. The schedule was set using
logic review meetings. The dates for each tasks are part of subcontracts.
If I start putting in actual start dates it move several tasks (start dates)
that are linked to it. The schedules are several pages long and I don't see
all the changes. Can I remove the logic so that I would have a gantt that
shows start/actual start/actual finish/finsh and % complete without corupting
the other start dates?
logic review meetings. The dates for each tasks are part of subcontracts.
If I start putting in actual start dates it move several tasks (start dates)
that are linked to it. The schedules are several pages long and I don't see
all the changes. Can I remove the logic so that I would have a gantt that
shows start/actual start/actual finish/finsh and % complete without corupting
the other start dates?