Hi All
I have asked this before and Rod McGill replied but I couldn't see his
attachment.
We are running Project Standard 2003 and Windows 2000. We have a resource
pool to which projects are linked. I have added a column in the Resource
Usage view for the resource pool called Project which shows the project name
associated with the particular tasks. Briefly, how can I remove the full path
(\\servername\folder\subfolder\filename.mpp) from this column so that it just
shows the actual project name.
Thanks again.
Mark
I have asked this before and Rod McGill replied but I couldn't see his
attachment.
We are running Project Standard 2003 and Windows 2000. We have a resource
pool to which projects are linked. I have added a column in the Resource
Usage view for the resource pool called Project which shows the project name
associated with the particular tasks. Briefly, how can I remove the full path
(\\servername\folder\subfolder\filename.mpp) from this column so that it just
shows the actual project name.
Thanks again.
Mark