M
ME
Using Project Server 2003 I was taught that you could remove a resource
from a project by changing the resource, in the resource sheet on the
project, from committed to proposed. I tested this and saw that the
project tasks are removed from the task sheet and that the project is
removed from the Project Center view. Without the project being
listed, it is difficult (but not impossible of course) for the resource
to get to the WSS site.
We just repeated the test and while the tasks are removed from the Task
view, the project name still shows up in the Project Center.
I am thinking that there is a permission that we missed that allows the
Project Center view even when there is no assignment.
Any ideas? TIA.
ME
from a project by changing the resource, in the resource sheet on the
project, from committed to proposed. I tested this and saw that the
project tasks are removed from the task sheet and that the project is
removed from the Project Center view. Without the project being
listed, it is difficult (but not impossible of course) for the resource
to get to the WSS site.
We just repeated the test and while the tasks are removed from the Task
view, the project name still shows up in the Project Center.
I am thinking that there is a permission that we missed that allows the
Project Center view even when there is no assignment.
Any ideas? TIA.
ME