Hello Eyal,

A work around: copy the resource's name into the Initials field on
the Resource Sheet. Then Format > Bar Styles, select the "Task" bar
style and on the Text tab, select Resource Initials instead of name.
Repeat as necessary for critical tasks.

I hope this helps. Let us know how you get along.