J
Joe
Is there a way to remove a specific task from PWA that is 100% complete
without removing other task items that are 100% Complete? Or not let a
resource enter hours on a specific task without having to delete it.
What I am trying to do is remove a specific task from an “administrativeâ€
project plan. Since all admin task are 100% complete, I don’t want to use
the Admin utility because it will remove all of the tasks that are complete,
which I don’t want to do.
If case you are wondering why I want to do this:
I have an admin project plan where people track unplanned hours on general
support type task. For example I may have a task called “Development
Support†which would be used when a resource needs to track hours they spent
helping another developer with something unrelated to a task on the plan.
Rather than creating specific task after the fact, we use an admin project
plan to track these types of situations. All of these tasks are set up as
100% complete because we don’t plan for it. (instead, I allocated resources
at 80%, the other 20% is typically used for these admin tasks).
In this case, I have a specific admin task that I don’t want people to track
time too anymore, but I don’t want to delete the task either because I don’t
want to lose the history.
If I can’t remove it from PWA, is there a way to prevent people from
entering time on a completed task on the timesheets?
without removing other task items that are 100% Complete? Or not let a
resource enter hours on a specific task without having to delete it.
What I am trying to do is remove a specific task from an “administrativeâ€
project plan. Since all admin task are 100% complete, I don’t want to use
the Admin utility because it will remove all of the tasks that are complete,
which I don’t want to do.
If case you are wondering why I want to do this:
I have an admin project plan where people track unplanned hours on general
support type task. For example I may have a task called “Development
Support†which would be used when a resource needs to track hours they spent
helping another developer with something unrelated to a task on the plan.
Rather than creating specific task after the fact, we use an admin project
plan to track these types of situations. All of these tasks are set up as
100% complete because we don’t plan for it. (instead, I allocated resources
at 80%, the other 20% is typically used for these admin tasks).
In this case, I have a specific admin task that I don’t want people to track
time too anymore, but I don’t want to delete the task either because I don’t
want to lose the history.
If I can’t remove it from PWA, is there a way to prevent people from
entering time on a completed task on the timesheets?