Remove Splits in a Baseline

T

terrapinie

There was a split task in the schedule when it was baselined. It
should not have been split. I have removed the split in the task but
want to also make the baseline not appear split. How can I do this
without rebaselining the whole schedule?
 
R

Rod Gill

Hi,

If you view tables with baseline data you can manually edit it.
Alternatively for later versions of Project, you can baseline only selected
tasks and if required their summary tasks.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
J

Jan De Messemaeker

Select the task, Tools, Tracking, Save Baseline, for selected tasks, OK.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top