A
Andy Bruncke
Is there a way to automatically remove all splits in tasks that have 0% work
completed? I leveled with splits on and it spread some tasks out in very
odd ways, and I want to sort of "start over". Short of manually going
through every task (15k +) and un-splitting them, is there a way to tell
project to do this for me?
Thanks
Andy