remove task splits

C

CharlieB

I have a master project composed of many subprojects with many tasks. After
leveling there are a great number of split tasks. These each have many
splits. OK nice exercise but I now want to restore them. Clearing leveling
takes out the delays but leaves the splits. I need an automated way to
remove all of the inserted splits. Does anyone have any ideas?
 
D

Dave

Clearing levelling should remove the splits. Have you tried clearing
levelling in each of the component files?

There is an option within levelling not to allow splits.
 