Hi
On almost all of our Programmes we include admin tasks such as Project
Management. These tasks need to last the entire programme even though actual
time may be put against it only once a week. Unfortunately Project for
obvious reasons calculates this to be the critical path, which in real life
it isn't. I have tried using a recurring task but it isn't suitable for our
needs. Is there a way that project can ignore certain tasks when calculating
the critical path or is there another method we can use?
Thanks
On almost all of our Programmes we include admin tasks such as Project
Management. These tasks need to last the entire programme even though actual
time may be put against it only once a week. Unfortunately Project for
obvious reasons calculates this to be the critical path, which in real life
it isn't. I have tried using a recurring task but it isn't suitable for our
needs. Is there a way that project can ignore certain tasks when calculating
the critical path or is there another method we can use?
Thanks