Remove tasks from resources simultaneously

T

Taj

I’m using PS 2003. I am the PM and have a project that I want to cancel. But
there are a few tasks that are assigned to resources. How do I remove the
task from the resources task list simultaneously?

I have tried –
- To un-assign tasks but that leaves the resource a task to hide all the
tasks from the list that I have unassigned.
- Republish and collaborate the project

Any ideas?

Thanks in advance for your help and time.
 
J

Jonathan Sofer

Change the booking type to "Proposed" first and re-publish. This will
remove all the assignments from the resources timesheet.

After you verified the tasks have been removed from the resource's
timesheets you can delete the assignments and resources if you want and
re-publish the plan.

Jonathan Sofer
 
T

Taj

Hi All,

Thanks for your help.

Jonathan I think what you have suggested would benefit me the most.

Thanks for your time.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top