C
Colleen
One of my managers says that when I send her the MSProject file and she
converts it to Excel that in addition to the start/finish dates, it puts in a
time in that field as well. For our project we are not dealing with time at
all, so all we need to know is the dates. She's been manually removing this
time from the field each week, but we are wondering if there is a way to
remove this time option so only dates appear in those columns? I look in the
project plan options and found an area to specify the working times, but when
I tried to delete both fields it would not allow me. It seems that a time
needs to be in both fields. Please confirm if there is a way to remove this
time stamp from the start/end date columns. Thanks!
Colleen
converts it to Excel that in addition to the start/finish dates, it puts in a
time in that field as well. For our project we are not dealing with time at
all, so all we need to know is the dates. She's been manually removing this
time from the field each week, but we are wondering if there is a way to
remove this time option so only dates appear in those columns? I look in the
project plan options and found an area to specify the working times, but when
I tried to delete both fields it would not allow me. It seems that a time
needs to be in both fields. Please confirm if there is a way to remove this
time stamp from the start/end date columns. Thanks!
Colleen