A
Alma Luera
if we make a mistake and post actual work values in the
Resource USage view, and we wantto correct them, MS
Project does not appear to allows us to clear the cells,
it only allows us to input "0hrs". With "0 hrs" in the
cell, our actual cost is correctly calculated, but since
the "actual work" is also posted in "work" and we cannot
clear these cells, the schedule is then effected, and we
cannot appear to change it.
Does anyone know a solution?
Resource USage view, and we wantto correct them, MS
Project does not appear to allows us to clear the cells,
it only allows us to input "0hrs". With "0 hrs" in the
cell, our actual cost is correctly calculated, but since
the "actual work" is also posted in "work" and we cannot
clear these cells, the schedule is then effected, and we
cannot appear to change it.
Does anyone know a solution?