C
cornasdf
Hey all,
I am having trouble in that my projects are still showing up on timesheets
and resource assignment views even after completion. I have a project that
is 100% complete as of late Jan 09. I have followed this post:
http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/PreventTimeEntry.aspx,
which had me mark all of my resources as proposed and republish to no avail.
Does anybody know a good way to mark projects completed without removing
them from project server entirely?
Using Project Server 2007 with the feb CU.
Thanks
ej
I am having trouble in that my projects are still showing up on timesheets
and resource assignment views even after completion. I have a project that
is 100% complete as of late Jan 09. I have followed this post:
http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/PreventTimeEntry.aspx,
which had me mark all of my resources as proposed and republish to no avail.
Does anybody know a good way to mark projects completed without removing
them from project server entirely?
Using Project Server 2007 with the feb CU.
Thanks
ej