A
Arashazadeh
I was advised to minimize constraints between tasks and allow the "A
Soon As Possible" to prevail. Now some of my resources have 156 hou
days at the beginning of the project. Have I taken the advice to
literally? or should I be using lag time and leveling delays to adjus
the schedule? Using the Gantt chart relationships (FF, FS,..) seem to b
the easiest way of doing this. What is the principle/rule of thumb tha
you would go by?
Thanks in advance
Soon As Possible" to prevail. Now some of my resources have 156 hou
days at the beginning of the project. Have I taken the advice to
literally? or should I be using lag time and leveling delays to adjus
the schedule? Using the Gantt chart relationships (FF, FS,..) seem to b
the easiest way of doing this. What is the principle/rule of thumb tha
you would go by?
Thanks in advance